Skip to main content
All Case Studies
Commercial Indianapolis, Indiana 10 days Industrial Property Owner

50,000 Sq Ft Warehouse Floor Coating: Fast-Cure Polyaspartic System with Minimal Downtime

1

Units Serviced

50%

Time Saved

$45,000

Cost Savings

50,000 Sq Ft Warehouse Floor Coating: Fast-Cure Polyaspartic System with Minimal Downtime

🔧 The Challenge

The warehouse floor had severe surface deterioration from 15 years of heavy forklift traffic, causing concrete dust that contaminated inventory and posed respiratory risks. The existing floor coating was peeling and creating trip hazards. The facility operated 24/5 and could only shut down sections for limited periods. Any coating system needed to withstand heavy forklift traffic, chemical spills, and thermal cycling while curing fast enough to minimize downtime.

💡 Our Solution

Auxi Services selected a polyaspartic coating system that cures in 2-4 hours versus 24-72 hours for traditional epoxy, allowing rapid return to service. The warehouse was divided into 5 zones, each completed sequentially. Surface preparation included diamond grinding and crack repair. A moisture mitigation primer was applied to address concrete moisture levels. The system included a base coat with anti-slip aggregate in traffic areas, a color coat for wayfinding, and a UV-stable topcoat. Temporary ramps allowed forklift access to completed zones while adjacent areas were worked on.

✅ The Outcome

Full 50,000 sq ft floor coating completed in 10 days. Facility maintained 70% operations throughout project. Polyaspartic coating withstood forklift traffic within 24 hours of application. Concrete dust eliminated entirely. Floor surface improved lighting reflection by 30%, reducing energy costs. Forklift tire wear reduced. Annual floor maintenance costs dropped by $12,000. Project completed $45,000 under budget.

Project Photos

Project photo 1

"Our floor was generating so much dust we were failing air quality inspections. Auxi came in, worked around our schedule, and had the entire 50,000 sq ft coated in 10 days. The polyaspartic system cured so fast we were running forklifts on it the next day. No more dust, no more issues."

— Karen Whitfield, Operations Director, Midwest Logistics Partners

Project Details

IndustryCommercial
LocationIndianapolis, Indiana
Timeline10 days
Client TypeIndustrial Property Owner
ServiceFlooring

Service Used

Multifamily Turn Services

Learn About This Service

Need similar results?

Let's talk about your property's needs.

View All Case Studies
AI Insights

AI-Powered Analysis

Our AI analyzed this project's results to surface key takeaways and actionable recommendations.

$45,000 Total Project Savings
Cost Analysis

Optimizing Operational Expenditure Through Targeted Maintenance

By selecting a high-durability polyaspartic coating, the facility eliminated recurring dust issues and reduced ongoing repairs. This strategic investment resulted in $12,000 annual maintenance savings and a project completion $45,000 under the estimated budget.

50% Reduction in Project Downtime
Timeline Optimization

Minimizing Operational Downtime With Rapid Curing Systems

The use of a polyaspartic system allowed for a 2-4 hour cure time, significantly faster than traditional epoxy. This enabled the facility to maintain 70% of its normal operations throughout the 10-day project duration.

30% Improvement in Lighting Reflection
Strategic Recommendation

Leverage Advanced Materials for Facility Longevity

Facilities facing heavy forklift traffic and high moisture should prioritize polyaspartic coatings to balance durability with operational continuity. Integrating specialized color coatings also enhances wayfinding and lighting efficiency, delivering long-term facility performance upgrades.

AI-generated analysis for reference only. Contact our team for a tailored operational assessment.

Case Study — FAQs

Common questions about this type of project.