250-Unit Multifamily Turnover: 40% Faster Completion with Coordinated Vendor Network
250
Units Serviced
40%
Time Saved
$125,000
Cost Savings

🔧 The Challenge
Property manager faced significant vacancy losses due to slow unit turnover. Previous vendor coordination process required sequential scheduling, creating bottlenecks. Poor communication between trades extended timelines and drove up costs. Timeline pressure was impacting NOI and creating tenant satisfaction issues.
💡 Our Solution
Auxi Services implemented coordinated vendor management system using a unified scheduling platform. Deployed certified electrical, plumbing, painting, and flooring contractors working simultaneously across property. Real-time progress tracking and proactive issue resolution minimized delays. Daily coordination meetings ensured seamless handoffs between trades. Quality assurance inspections at each stage prevented rework.
✅ The Outcome
Completed all 250 units in 9.6 weeks vs. 16-week historical average. Average cost per unit reduced 18%. Zero quality defects in final inspection. Property achieved 92% occupancy within 2 months of completion. Positive online reviews from new residents contributed to 15% reduction in marketing spend.
Project Photos
"Auxi's vendor coordination completely transformed our turnover process. We went from 16 weeks to under 10 weeks while actually improving quality. The cost savings alone paid for their service within the first month."
— Jennifer Martinez, Director of Operations, Atlanta Property Group
Project Details
AI-Powered Analysis
Our AI analyzed this project's results to surface key takeaways and actionable recommendations.
Parallel Scheduling Accelerates Unit Turnover Speed
By shifting from sequential to coordinated parallel scheduling, the platform eliminated idle time between trade handoffs. This transition allowed for a 40% reduction in total project duration, moving from a 16-week historical average to just under 10 weeks.
Lowering Overhead Through Reduced Vacancy Duration
Efficiency gains across multiple trade disciplines resulted in direct savings of $125,000 for the client. Beyond labor costs, the rapid turnover significantly decreased vacancy losses and lowered subsequent marketing expenditures by 15%.
Standardizing Quality Assurance Protocols Prevents Costly Rework
Property managers should adopt integrated quality assurance inspections at every stage of the turnover process to ensure zero defects upon delivery. This proactive approach not only maintains high standards but also protects net operating income by avoiding the costs associated with post-completion repairs.
AI-generated analysis for reference only. Contact our team for a tailored operational assessment.