120-Room Boutique Hotel Renovation: Off-Season Completion with Zero Revenue Loss
120
Units Serviced
20%
Time Saved
$320,000
Cost Savings

🔧 The Challenge
The hotel had not been renovated in 12 years and was losing market share to newer competitors. Guest reviews cited outdated rooms, worn carpeting, and aging bathrooms. The ownership group needed a complete renovation but could only close for 10 weeks during the off-season. The project required coordination of flooring, painting, bathroom fixtures, furniture installation, lighting, and millwork across 120 rooms plus lobby and corridor areas.
💡 Our Solution
Auxi Services deployed 6 simultaneous work crews, each handling a floor of 20 rooms. A just-in-time material delivery system eliminated storage issues. Daily quality inspections ensured consistent standards across all rooms. A dedicated project manager coordinated all trades, and a real-time progress dashboard gave ownership group visibility. Furniture, fixtures, and equipment (FF&E) were pre-staged off-site for rapid installation.
✅ The Outcome
All 120 guest rooms and common areas renovated in 8 weeks, 2 weeks ahead of schedule. Guest satisfaction scores jumped from 3.2 to 4.6 out of 5. Average daily rate increased by 18%. Occupancy rates rose 22% in first quarter post-renovation. Project completed $320,000 under budget. Hotel reopened 2 weeks early, capturing additional peak-season revenue.
Project Photos
"We went from one of the lowest-rated hotels in our market to a top-3 property in just 8 weeks. Auxi's coordination was flawless — every trade showed up on time, every room was ready when promised, and the quality was exceptional. The early completion paid for itself."
— Margaret Sullivan, VP of Operations, Harmony Hotel Group
Project Details
AI-Powered Analysis
Our AI analyzed this project's results to surface key takeaways and actionable recommendations.
Optimized Procurement Drives Significant Capital Savings
By implementing a just-in-time delivery system and off-site staging, we eliminated the need for costly on-site storage. This disciplined approach to logistics resulted in a total project savings of $320,000, directly improving the client's return on investment.
Parallel Workflow Execution Accelerates Project Delivery
Deploying six simultaneous work crews allowed for a compressed construction schedule that beat the initial 10-week deadline by two full weeks. This efficiency enabled the hotel to capitalize on peak-season revenue earlier than anticipated, preventing potential income loss.
Real-Time Visibility Drives Superior Asset Performance
Maintaining a centralized project dashboard allowed ownership to track progress accurately, ensuring consistent quality across all 120 rooms. Firms undertaking major renovations should prioritize digital oversight to boost guest satisfaction scores and drive higher average daily rates.
AI-generated analysis for reference only. Contact our team for a tailored operational assessment.